The UK’s cloud and data centre infrastructure landscape is undergoing significant strain, driven by surging AI demand, energy market volatility, and grid connectivity bottlenecks.
For businesses reliant on these services, the resulting pricing shifts, capacity constraints, and contractual complexities require urgent strategic adaptation.
This report analyses critical trends and provides actionable insights for decision-makers navigating this evolving environment.
Latest Incidents Affecting UK Users
-
Grid connection delays: The National Energy Systems Operator (NESO) has suspended new applications until 2037 due to a backlog of 400 GW in requests, stalling major projects like Microsoft’s £2.5 billion UK data centre expansion .
-
Colocation cost surges: Energy price hikes have tripled power fees for some UK colocation customers, with one firm reporting a jump from £900 to £2,400/month.
-
Cloud price adjustments: Microsoft Azure announced a 5-6% price drop for UK customers from February 2025, while AWS plans increases for compute and storage services, citing infrastructure and sustainability costs.
-
Construction delays: Supply chain constraints and planning reforms have slowed data centre builds, with 53% of European operators warning of insufficient capacity to meet AI-driven demand.
Pricing outlook
-
Colocation: Energy pass-through clauses are becoming standard, with providers shifting rising power costs (up to 10x wholesale electricity prices) to customers. Cooling and backup generator expenses compound these hikes.
-
Cloud services: Hyperscalers are diverging. Microsoft’s GBP-adjusted Azure cuts contrast with AWS’s planned increases for EC2 instances (up 8-12%) and data egress (up 15%). Enterprises with Azure Consumption Commitments (MACCs) may struggle to meet targets post-price reduction.
-
Contract negotiations: Fixed-term agreements are increasingly rare. Providers now favour flexible terms with inflation-linked escalators and penalties for early termination.
Availability issues
-
Grid dependency: London’s M25 corridor faces acute shortages, with wait times exceeding 12 years for new connections. Regional alternatives (e.g., South Wales, Northern England) offer shorter lead times but lack hyperscale readiness.
-
AI-driven capacity crunch: High-density GPU clusters require 30-50% more power per rack, forcing providers to prioritise AI workloads over traditional cloud clients. Pre-booking 18-24 months ahead is now standard.
-
Retrofit limitations: 66% of operators are upgrading existing facilities, but noise regulations and cooling upgrades (liquid systems cost 2x air-cooled) constrain output.
Impact on Existing Usage
-
“Noisy neighbour” risks: Colocation clients report 22% longer latency peaks as providers over-subscribe racks to offset energy costs. SLAs increasingly exclude performance guarantees during peak AI processing windows.
-
Renegotiation pressure: Legacy contracts face mid-term reviews, with 43% of firms reporting unexpected surcharges for power or cooling upgrades.
Outlook for 2025–2026
-
Grid reforms: The Planning and Infrastructure Bill aims to cut connection waits by seven years via fast-tracked approvals, but tangible improvements are unlikely before 2027.
-
Energy diversification: On-site microgrids (solar/wind) may offset 15-20% of grid dependency, though planning barriers persist.
-
Regional disparities: Scotland and Northern Ireland will gain prominence as “AI readiness zones” with tax incentives, while London’s dominance wanes due to infrastructure fatigue.
Global Context
-
FLAPD cities: Frankfurt, Amsterdam, and Paris face similar grid delays (8-10 years), pushing demand to secondary markets like Berlin and Marseille.
-
US comparison: Texas and Virginia offer 40% lower power costs but lack GBP-denominated pricing stability, creating currency risk for UK firms.
-
Asia-Pacific: Singapore’s moratorium on new data centres and Mumbai’s grid instability make Tokyo and Seoul preferred hubs, albeit with 25% premium pricing.
Strategic Recommendations
-
Diversify providers: Blend hyperscale (Azure/AWS) with regional UK colocation to mitigate single-point failures.
-
Lock in energy terms: Negotiate fixed-price power clauses or hybrid models with colocation partners.
-
Pre-book capacity: Secure 2026–2027 slots now in emerging zones (e.g., Glasgow, Cardiff) to avoid 2030+ waits.
-
Monitor regulatory shifts: The UK’s Critical National Infrastructure designation may unlock subsidies for early adopters of on-site renewables.
The collision of AI’s exponential demand and infrastructure’s linear growth mandates proactive adaptation. Firms that institutionalise flexibility in contracts, geography, and energy sourcing will gain resilience in this volatile market.
Peter is also CEO of Flexiion and has a number of other business interests. (c) 2025, Peter Osborn